Forming foundations of America’s Cup village
A huge cargo of steel piles has been unloaded in Dockyard as part of the South Basin project.
The piles will be drilled into the seabed to secure the reclaimed land that will form the foundations of the America’s Cup village.
The steelwork arrived in the West End last week on board the BBC Tennessee from Baltimore in the United States. Project managers expect to start driving the piles into the earth within the next couple of weeks.
Andrew Dias, the general manager of the West End Development Corporation, told The Royal Gazette that the project was “progressing well” and remained on time and on budget.
“The steel as well as the other infrastructure is now on site, although obviously not on the reclaimed land as the aggregate is still being spread out,” he said.
“We have taken delivery of 2.15 tonnes of steel piles, 1,726 sheet piles, 37 Y-shaped piles and 39 anchor piles.
“The steel work to create the perimeter is expected to take around eight weeks to complete, at which time a concrete cap will be added to the steel structure.”