The holiday, which to many Bermudians represents the start of summer, traditionally is also the first day locals go swimming.But plans by the Ministry of Works to have construction work completed before the holiday have fallen through.

24.

The holiday, which to many Bermudians represents the start of summer, traditionally is also the first day locals go swimming.

But plans by the Ministry of Works to have construction work completed before the holiday have fallen through.

A Ministry spokeswoman blamed the late arrival of roofing material and plumbing supplies for delay.

Plans for upgrading the 25-year-old toilet block, emerged in July, 1998 after National Liberal Party official Graeme Outerbridge described the situation as horrendous.

The work is now expected to be complete by mid-June.