In-principle approval recommended for Elbow Beach
Planning officials have recommended in-principle approval to progress with plans to redevelop Elbow Beach, with conditions.
The Loren Hotel Group announced last year that it intended to revitalise the shuttered hotel site, creating a five-star resort with a 75-key hotel and a combination of cottages, villas and estate homes.
In a report prepared for the Development Applications Board, which is set to consider the in-principle plans next week, a technical officer recommended that the plans be given the green light.
The report said: “Having considered the proposed development, the consultation responses and the representations received, the department considers the proposed use, siting and layout, density, site coverage and building height acceptable in principle, subject to the recommended conditions.
“The application seeking final planning approval will provide the opportunity to assess the reserved matters, including building lines, detailed design and external appearance, parking, access and landscaping, together with the outstanding technical details identified.”
The recommended conditions include that the board reserves final approval for all details, with the application for the approval of “reserved matters” made within two years.
The report added that the final planning application should include a post-demolition topographical survey, a comprehensive landscape plan, a conservation management plan and a Bermuda skink survey.
A staff accommodation plan must also be submitted with the planning application, along with details for the proposed wastewater treatment plant.
The property was purchased by The Loren Group last year with the intention of running it and its redeveloped Pink Beach hotel property as a single hotel with two locations.
The planning application, submitted this summer, detailed significant changes to the South Shore hotel property, which closed its doors in 2020.
The vast majority of structures now standing on the site would be demolished as part of the revitalisation project, including the main hotel building.
However, the building at Mickey’s Bar and Grill would be refurbished and reopened, while the western boundary beach wall, some perimeter walls and a house at the northern end of the property would be retained.
The new main hotel, referred to as the clubhouse, would be a seven-storey building located in the southwest corner of the property with 76 guest rooms and amenities including spa facilities, a ballroom, meeting room, café and a rooftop bar-restaurant.
The 22 residences, meanwhile, would be built on the hillside overlooking South Shore with the smallest units closer to the water.
Each of the units would be required to be used as part of the hotel’s inventory for at least six months of the year.
The property’s one-way traffic loop will be replaced with a new two-way driveway along the western side of the site, allowing hotel guests and visitors access to the hotel and clubhouse.
Meanwhile, access to the public portion of Elbow Beach would be “maintained and enhanced”.