Bids under evaluation for Swing Bridge replacement

A detour route is being built at the East End to facilitate works for a replacement Swing Bridge (File photograph by Akil Simmons)

Bids for the construction of a replacement Swing Bridge in the East End are under review, MPs heard today.

Jaché Adams, the Minister of Public Works and Environment, told the House of Assembly that the ministry has reached an agreement “in principle” with a landowner at Stokes Point in St George’s on a purchase required for the project.

He said the site, costing the Government about $100,000, was earmarked as the most “suitable landing point” for the new bridge.

Several procurement processes were undertaken to kick-start the project, including hiring a contractor to refurbish the former Bridge Operator’s Hut and a contract for an engineering firm to provide independent oversight.

“Perhaps most importantly, Government invited experienced contractors to bid for construction of the new bridge,” Mr Adams added.

Noting the “specialised nature” of the project, he said the Government expected international interest and “actively encouraged overseas companies to partner with Bermudian businesses wherever possible”.

The move would create local opportunities while allowing Bermudians to gain skills and experience from a major infrastructure project.

An update on the bridge construction schedule will come after procurement is completed and contracts are in place.

Mr Adams reminded MPs of the bridge’s mechanical issues in the past.

The new structure will use a modern hydraulic system to raise and lower the bridge, with emergency valves that can be released to lower the bridge if problems arise.

The older structure will remain in use while the new crossing is being constructed. Once the replacement is fully operational and open to traffic, the decommissioning of the prior bridge will commence.

In response to a question from Vance Campbell, the Shadow Minister of Public Works and Infrastructure on alternatives should the ageing bridge prove unsuitable, Mr Adams said: “We do have the likelihood of failure is minimal.”

Structural engineers “have consistently stated” that the bridge should be able to last, Mr Adams said.

However, he noted that “anything can happen” and that contingency plans were in place.

Update on works at Gibbs Hill Lighthouse

Safety railing works at the Gibbs Hill Lighthouse have been completed, MPs heard today.

Jaché Adams, the Minister of Public Works and Environment, said works within the restaurant area, including upgrades to their fire alarm system were also completed.

He said recent inspections of the lighthouse roof identified leakages.

He said the issue is being addressed, adding that it must be resolved before the works on the beacon can proceed.

The painting of the lighthouse is expected to commence shortly, he added.

In other updates, Mr Adams said roadworks are under way in the area and temporary traffic changes have been introduced.

A smaller roundabout is being built near the existing structure to replace the larger roundabout and free up the space needed for construction of the new bridge.

Road realignment works commenced in late May with the construction of the temporary bus turnaround within Kindley Field Park (Photograph by Akil Simmons)

Traffic entering St David’s is using a one-way route along St David’s Road, while motorists leaving the area are travelling along Southside Road through Kindley Field Park.

Mr Adams said a new bus lay-by has been constructed across from the Double Dip Restaurant and will be used once the new roundabout and associated traffic changes are completed.

“We expect all of these traffic adjustments to be completed during October of this year, weather permitting,” he added.

Mr Adams acknowledged concerns raised by residents about the level of lighting along Southside Road through Kindley Field, and said the ministry was working to address them.

He said other considerations had to be taken into account first, adding: “We are working through those issues and will provide further information once that work has been completed.”

Royal Gazette has implemented platform upgrades, requiring users to utilize their Royal Gazette Account Login to comment on Disqus for enhanced security. To create an account, click here.

You must be Registered or to post comment or to vote.

Published September 11, 2026 at 7:41 pm (Updated September 11, 2026 at 7:41 pm)